2.5 Dates, Times and Durations
The PPS uses the following kinds of time value. All times are local times at the production site; the PPS does not adjust for daylight saving.
- A date is a calendar date, for example 2027-01-04.
-
A date-time is a date together with a time of day, for example 2027-01-04 07:30. The PPS works to a resolution of one minute; seconds are ignored.
When a date is given where a date-time is expected, it is interpreted as follows:
- for values that mark the start of a period (for example the release date of an order) the time is the start of the day, 00:00;
- for values that mark the end of a period (the due date of an order, the end date of the horizon and the latest finish of maintenance) the time is the end of the day, i.e. 00:00 on the following day.
So an order that is due on 2027-01-08 is on time if it is completed at any time on that day.
- A day time is a time of day on the 24-hour clock, for example 15:30. Day times are used to define shifts.
- A duration is an elapsed period of time in hours and minutes, for example 2:30. Durations may exceed 24 hours.