2.13 Order Precedences
An order precedence links two different orders. By default it states that the after order cannot start until the before order is complete. Either side may instead name a particular operation: for example, the assembly operation of one order may need to wait for the order that makes its sub-assemblies. An order precedence may also have a minimum delay.
If the before order cannot be scheduled, then neither can the after order. The order precedences must not form a cycle.