2.19 Capacity Planning

In planning mode, the horizon is divided into consecutive time buckets of a fixed number of days, starting on the start date. (The last bucket may be shorter.) Each operation is assigned to a single time bucket and a single resource, and detailed timing within the bucket is not considered.

Each operation has a work content: the number of hours of capacity it consumes. This defaults to its duration in hours multiplied by the number of staff it needs (or by one if it needs no staff), so capacities are effectively given in labour hours for staffed operations and machine hours otherwise.

Each resource has two capacities, in hours, for each day of the horizon:

  • a hard capacity, which is never exceeded;
  • a soft capacity, which should not be exceeded but may be at a cost (for example by working overtime).

The capacity of a resource in a bucket is the sum of its capacities on the days of the bucket. A resource’s daily capacities are its default capacities on each working day of its calendar (or on every day, if it has no calendar) and zero on other days, unless they are overridden for particular dates in the Capacities sheet.

Precedences are approximated in planning mode: the after operation must be in the same bucket as the before operation or a later one. A minimum delay of d days means that the after operation’s bucket must be at least d divided by the bucket size (rounded down) buckets after the before operation’s. For example, with weekly buckets a delay of 2 days allows both operations to be in the same week, but a delay of 7 days requires the after operation to be in the following week or later. Maximum delays and progress thresholds are ignored.

An order’s probability is used to select the orders to plan: orders whose probability is below the probability threshold are left out. By running a scenario with different thresholds, a planner can see the load under optimistic and pessimistic assumptions about which quotes will be won.

Staff, absences, set-up times, changeovers, shutdowns, maintenance and fixed starts are ignored in planning mode; use the Capacities sheet to reduce capacity on particular days instead.