2.18 Rescheduling
Production rarely goes exactly to plan. The PPS can reschedule: build a new schedule part-way through the horizon that takes account of the work already done.
A scenario for rescheduling gives the current time and the status of the operations that have started. Each operation has one of the following statuses:
- NOT_STARTED: the operation has not started. This is the default. It is scheduled at or after the current time.
- IN_PROGRESS: the operation has started and continues from the current time on its current resource. Its remaining duration is reduced according to its progress.
- COMPLETE: the operation is finished. It is not scheduled again and its precedences are treated as satisfied.
- ON_HOLD: the operation cannot be carried out at present, for example because it is waiting on a design change or a quality problem. It is not scheduled, nor are any of the operations that must follow it. Operations of the order that do not depend on it may still be scheduled.
An operation may also be given a fixed start, for example because it has been promised to a customer who wishes to witness it. The PPS must start it at exactly that time.