A Example Workbooks

The following example workbooks accompany this document. The basic example describes a small fabrication shop that makes brackets, frames and cabinets with seven resources over three weeks. Each extension builds on the previous one by adding the sheets and columns for one more feature; the exception is extension 8, which is a separate capacity planning example.

Workbook

Demonstrates

pps_template.xlsx

Every input sheet, with headers only.

pps_basic.xlsx

Configuration, resources (including a group and resources with a capacity greater than one), routings with per-unit durations, and orders with an extra Customer column.

pps_basic_solution.xlsx

The output for the basic example.

pps_extension_1.xlsx

Routing precedences: parallel operations, minimum and maximum delays and a progress threshold.

pps_extension_2.xlsx

Shifts and shift patterns used as resource calendars, including two shifts a day and a shift that ends at midnight; non-interruptible operations.

pps_extension_3.xlsx

Staff with skills and shift patterns, staffed operations and absences.

pps_extension_4.xlsx

Set-up times, order families (paint colours) and changeovers.

pps_extension_5.xlsx

A resource shutdown, a site-wide shutdown and maintenance.

pps_extension_6.xlsx

Order operations (a required resource, a longer duration, a skipped operation and late materials) and order precedences.

pps_extension_7.xlsx

Rescheduling from a current time, with completed and in-progress operations, an operation on hold, a fixed start and a new rush order.

pps_extension_8.xlsx

Capacity planning over twelve weeks in weekly buckets, with probability-weighted orders, default capacities and capacity overrides for a public holiday, a refit and reduced hours.

Table 3: Example workbooks.

Each workbook has an About sheet describing it; the PPS ignores this sheet.

The basic solution was produced by a simple heuristic that schedules the orders one at a time in priority order. It illustrates the output format, but it is not an optimised schedule. Because the basic example does not give the resources a calendar, they are available around the clock.