4.6 Sheet: Order Operations
This sheet gives order-specific data for some of the operations of some orders, including the status and progress of work already under way. Each row describes one operation of one order; an operation of an order may appear in at most one row. Operations that do not appear in this sheet are as defined by the order’s routing, and have not started.
This sheet is not required.
4.6.1 Column: Order
Required: Yes.
Type: Identifier.
Description: The identifier of an order in the Orders sheet.
4.6.2 Column: Operation
Required: Yes.
Type: Identifier.
Description: The identifier of an operation of the order’s routing.
4.6.3 Column: Resource
Required: If the status is IN_PROGRESS and the routing gives a resource group; otherwise no.
Type: Identifier.
Default: The resource or group given by the routing.
Description: The resource or resource group on which the operation must be carried out for this order. For an
operation that is in progress, this is the resource on which it is being carried out.
4.6.4 Column: Duration
Required: No.
Type: Excel duration.
Default: The total duration calculated from the routing.
Description: The total duration of the operation for this order. A duration of zero skips the operation.
4.6.5 Column: Staff
Required: No.
Type: Number (non-negative integer).
Default: The number of staff given by the routing.
Description: The number of staff needed for the operation for this order.
4.6.6 Column: Available From
Required: No.
Type: Excel date or date-time.
Default: The order’s release date.
Description: The time before which the operation cannot start, for example because materials or components will not
be available until then.
4.6.7 Column: Status
Required: No.
Type: Text: one of NOT_STARTED, IN_PROGRESS, COMPLETE or ON_HOLD.
Default: NOT_STARTED.
Description: The status of the operation.
4.6.8 Column: Progress
Required: No.
Type: Percentage.
Default: 0.
Description: For an operation that is IN_PROGRESS, the percentage of the operation’s duration that has been
completed. The operation’s remaining duration is reduced accordingly; for example, an operation of 10 hours that is
40% complete has 6 hours remaining. Ignored for other statuses.
4.6.9 Column: Fixed Start
Required: No.
Type: Excel date-time.
Default: The PPS chooses the start time.
Description: The time at which the operation must start. Must not be before the current time. Only allowed for
operations that are NOT_STARTED. Ignored in planning mode.

