4.6 Sheet: Order Operations

This sheet gives order-specific data for some of the operations of some orders, including the status and progress of work already under way. Each row describes one operation of one order; an operation of an order may appear in at most one row. Operations that do not appear in this sheet are as defined by the order’s routing, and have not started.

This sheet is not required.

4.6.1 Column: Order

Required: Yes.
Type: Identifier.
Description: The identifier of an order in the Orders sheet.

4.6.2 Column: Operation

Required: Yes.
Type: Identifier.
Description: The identifier of an operation of the order’s routing.

4.6.3 Column: Resource

Required: If the status is IN_PROGRESS and the routing gives a resource group; otherwise no.
Type: Identifier.
Default: The resource or group given by the routing.
Description: The resource or resource group on which the operation must be carried out for this order. For an operation that is in progress, this is the resource on which it is being carried out.

4.6.4 Column: Duration

Required: No.
Type: Excel duration.
Default: The total duration calculated from the routing.
Description: The total duration of the operation for this order. A duration of zero skips the operation.

4.6.5 Column: Staff

Required: No.
Type: Number (non-negative integer).
Default: The number of staff given by the routing.
Description: The number of staff needed for the operation for this order.

4.6.6 Column: Available From

Required: No.
Type: Excel date or date-time.
Default: The order’s release date.
Description: The time before which the operation cannot start, for example because materials or components will not be available until then.

4.6.7 Column: Status

Required: No.
Type: Text: one of NOT_STARTED, IN_PROGRESS, COMPLETE or ON_HOLD.
Default: NOT_STARTED.
Description: The status of the operation.

4.6.8 Column: Progress

Required: No.
Type: Percentage.
Default: 0.
Description: For an operation that is IN_PROGRESS, the percentage of the operation’s duration that has been completed. The operation’s remaining duration is reduced accordingly; for example, an operation of 10 hours that is 40% complete has 6 hours remaining. Ignored for other statuses.

4.6.9 Column: Fixed Start

Required: No.
Type: Excel date-time.
Default: The PPS chooses the start time.
Description: The time at which the operation must start. Must not be before the current time. Only allowed for operations that are NOT_STARTED. Ignored in planning mode.