4.4 Sheet: Routing Precedences
This sheet defines precedences between the operations of a routing. Each row defines one precedence. For a routing that has any rows in this sheet, all of its precedences must be given here; the default, sequential order of its operations no longer applies.
This sheet is not required.
4.4.1 Column: Routing
Required: Yes.
Type: Identifier.
Description: The identifier of a routing in the Operations sheet.
4.4.2 Column: Before
Required: Yes.
Type: Identifier.
Description: The identifier of the operation of the routing that must be done first.
4.4.3 Column: After
Required: Yes.
Type: Identifier.
Description: The identifier of the operation of the routing that must be done second. Must be different from
Before.
4.4.4 Column: Minimum Delay
Required: No.
Type: Excel duration.
Default: 0:00.
Description: The minimum elapsed time between the finish of the before operation and the start of the after
operation.
4.4.5 Column: Maximum Delay
Required: No.
Type: Excel duration.
Default: No maximum.
Description: The maximum elapsed time between the finish of the before operation and the start of the after
operation. Must not be less than the minimum delay. Ignored in planning mode.
4.4.6 Column: Progress Threshold
Required: No.
Type: Percentage.
Default: 100 (the before operation must finish).
Description: The after operation may start once the before operation is this percentage complete. Must not be given
together with a minimum delay. Ignored in planning mode.