4.15 Sheet: Capacities

This sheet overrides the default capacities of resources on particular days, for capacity planning. Each row gives the capacities of one resource on one day. For example, a row with a hard capacity of zero can be used for a public holiday or a planned shutdown.

This sheet is not required, and is ignored in scheduling mode.

4.15.1 Column: Resource

Required: Yes.
Type: Identifier.
Description: The identifier of a resource in the Resources sheet.

4.15.2 Column: Date

Required: Yes.
Type: Excel date.
Description: The day to which the capacities apply. Each resource and date may appear at most once.

4.15.3 Column: Hard Capacity

Required: Yes.
Type: Number (non-negative).
Description: The hard capacity, in hours, of the resource on that day.

4.15.4 Column: Soft Capacity

Required: No.
Type: Number (non-negative).
Default: The hard capacity.
Description: The soft capacity, in hours, of the resource on that day. Must not be greater than the hard capacity.