4.15 Sheet: Capacities
This sheet overrides the default capacities of resources on particular days, for capacity planning. Each row gives the capacities of one resource on one day. For example, a row with a hard capacity of zero can be used for a public holiday or a planned shutdown.
This sheet is not required, and is ignored in scheduling mode.
4.15.1 Column: Resource
Required: Yes.
Type: Identifier.
Description: The identifier of a resource in the Resources sheet.
4.15.2 Column: Date
Required: Yes.
Type: Excel date.
Description: The day to which the capacities apply. Each resource and date may appear at most once.
4.15.3 Column: Hard Capacity
Required: Yes.
Type: Number (non-negative).
Description: The hard capacity, in hours, of the resource on that day.
4.15.4 Column: Soft Capacity
Required: No.
Type: Number (non-negative).
Default: The hard capacity.
Description: The soft capacity, in hours, of the resource on that day. Must not be greater than the hard
capacity.