2.10 Precedences and Delays

A precedence between two operations of a routing states that one operation (the before operation) must finish before the other (the after operation) can start.

If a routing has no precedences, its operations are carried out one after the other, in the order in which they are listed in the Operations sheet. If a routing has precedences, then they replace that default order and only the given precedences apply. This allows operations to be carried out in parallel; for example, the parts of a cabinet may be milled and welded at the same time if both operations need only wait for cutting to finish. The precedences of a routing must not form a cycle.

A precedence can also specify:

  • a minimum delay: the after operation cannot start until at least this much time has elapsed since the before operation finished. Delays are elapsed (calendar) time, not working time, and are used for processes that take time but do not need a resource, such as curing, drying, cooling or outsourced work.
  • a maximum delay: the after operation must start no more than this much time after the before operation finishes. For example, welded parts may need to be painted within a day to stop them from rusting.
  • a progress threshold: instead of waiting for the before operation to finish, the after operation may start once the before operation is at least this percentage complete. This allows overlapping operations, for example starting to mill the first parts of a batch while the rest are still being cut. The after operation is also prevented from finishing before the before operation. A precedence with a progress threshold cannot also have a minimum delay.