2.20 Objectives
The PPS must satisfy all of the following constraints: resource capacities and calendars; precedences and delays; release dates and availability times; staff skills, rosters and absences; shutdowns; maintenance windows; fixed starts; and the planning horizon (and, in planning mode, hard capacities). Within those constraints it optimises the following objectives, in order of importance:
- Schedule as many orders as possible, preferring orders of higher priority.
- Minimise the total lateness of orders, weighted by priority. (An order with priority 1 has a weight of 10, priority 2 a weight of 9, and so on, down to a weight of 1 for priority 10.)
- In scheduling mode, minimise the total time spent on set-ups and changeovers. In planning mode, minimise the total load in excess of soft capacity.
- In scheduling mode, complete orders as early as possible. In planning mode, balance the load across time buckets.
The PPS searches for a good solution until it reaches its time limit, and returns the best solution it has found.