2.20 Objectives

The PPS must satisfy all of the following constraints: resource capacities and calendars; precedences and delays; release dates and availability times; staff skills, rosters and absences; shutdowns; maintenance windows; fixed starts; and the planning horizon (and, in planning mode, hard capacities). Within those constraints it optimises the following objectives, in order of importance:

  1. Schedule as many orders as possible, preferring orders of higher priority.
  2. Minimise the total lateness of orders, weighted by priority. (An order with priority 1 has a weight of 10, priority 2 a weight of 9, and so on, down to a weight of 1 for priority 10.)
  3. In scheduling mode, minimise the total time spent on set-ups and changeovers. In planning mode, minimise the total load in excess of soft capacity.
  4. In scheduling mode, complete orders as early as possible. In planning mode, balance the load across time buckets.

The PPS searches for a good solution until it reaches its time limit, and returns the best solution it has found.