4.3 Sheet: Operations
This sheet defines the routings. Each row defines one operation of a routing; a routing is the set of rows with the same Routing identifier. If the routing has no routing precedences, its operations are carried out in the order of the rows.
This sheet is required.
4.3.1 Column: Routing
Required: Yes.
Type: Identifier.
Description: The identifier of the routing that this operation belongs to.
4.3.2 Column: Operation
Required: Yes.
Type: Identifier.
Description: An identifier for the operation that is unique within its routing.
4.3.3 Column: Resource
Required: Yes.
Type: Identifier.
Description: The identifier of the resource, or resource group, on which the operation is carried out. If a group is
given, the operation is carried out on any one of the resources in the group.
4.3.4 Column: Duration
Required: No.
Type: Excel duration.
Default: 0:00.
Description: The fixed part of the duration of the operation, which does not depend on the order quantity.
4.3.5 Column: Duration Per Unit
Required: No.
Type: Excel duration.
Default: 0:00.
Description: The duration of the operation for each unit of the order’s quantity. The total duration of the operation
for an order is Duration plus Quantity times Duration Per Unit. If the total is zero, the operation is
skipped.
4.3.6 Column: Setup Time
Required: No.
Type: Excel duration.
Default: 0:00.
Description: The set-up time needed on the resource immediately before the operation. Ignored in planning
mode.
4.3.7 Column: Resource Units
Required: No.
Type: Number (positive integer).
Default: 1.
Description: The number of units of the resource that the operation occupies. Must not be greater than the resource’s
capacity (or, for a group, the capacity of each resource in the group).
4.3.8 Column: Staff
Required: No.
Type: Number (non-negative integer).
Default: 0.
Description: The number of staff needed to carry out the operation.
4.3.9 Column: Skill
Required: If Staff is greater than zero and the scenario has a Staff sheet.
Type: Identifier.
Description: The skill that each of the operation’s staff must have.
4.3.10 Column: Work Content
Required: No.
Type: Number (non-negative).
Default: The total duration in hours, multiplied by the number of staff (or by one if the operation needs no
staff).
Description: The number of hours of capacity that the operation consumes, for one order. Only used in planning
mode.
4.3.11 Column: Interruptible
Required: No.
Type: Yes/no.
Default: Yes.
Description: Whether the operation may be interrupted by breaks in working time.
4.3.12 Column: Description
Required: No.
Type: Text.
Description: A description of the operation, for the user’s reference.