2.15 Set-up Times and Changeovers
A set-up is preparation of a resource before an operation, such as loading a program and fixtures on a machine. Set-up occupies the resource (and the operation’s staff) immediately before the operation starts.
The set-up time of an operation is the sum of:
- its setup time, which applies every time the operation is carried out; and
- the changeover time from the family of the previous operation carried out on the same resource unit to the family of this one, if they differ.
Changeover times are sequence dependent: for example, changing a paint booth from black to white may take much longer than changing it from white to black. The PPS sequences operations to reduce the total time spent on set-ups.