1 Overview

The Opturion Production Planning and Scheduling optimiser (PPS) builds production plans and schedules for make-to-order manufacturing and other multi-step processing operations. It takes a set of orders, each of which must be processed through a sequence or network of operations, together with a description of the resources (machines, work centres, bays, cells), the staff and the working time that are available to do that work. It decides when, and on which resources, each operation is carried out so as to complete as many orders as possible by their due dates.

The PPS has two modes of operation:

  1. Scheduling: the PPS builds a detailed schedule giving the start and finish time, the resource and the staff for every operation. Scheduling takes account of resource capacities and calendars, staff skills and rosters, set-up and changeover times, shutdowns, maintenance and the progress of work that is already under way.
  2. Planning: the PPS builds a rough-cut capacity plan, assigning each operation to a time bucket (typically a week) and comparing the resulting load against the capacity of each resource. Planning is much faster than scheduling and is intended for answering questions such as “can we accept this order and still meet its due date?” or “which work centres will be overloaded next month?”. It can include potential orders (quotes) weighted by their probability of being won.

This document describes the data model used by the PPS and the Microsoft Excel formats for its input (Section 4) and output (Section 5). A set of example workbooks that illustrate each feature in turn is described in Appendix A.