3.18 Sheet: Assignments
The Assignment sheet is used to define any existing assignment of jobs to crews.
Each row represents an assignment of a job to a crew.
This sheet is not required if there are no assignments.
3.18.1 Column: Job
Required: Yes.
Type: Text or (integer) number.
Description: The identifier for the job.
3.18.2 Column: Crew
Required: Yes.
Type: Text or (integer) number.
Description: The identifier for the crew.
3.18.3 Column: Start Time
Required: Yes.
Type: Excel date time.
Description: The time the job is planned to start.
3.18.4 Column: Finish Time
Required: Yes.
Type: Excel date time.
Description: The time the job is planned to finish.
3.18.5 Column: Flex
Required: Yes.
Type: Number.
Description: A number between 0 and 1 (inclusive), which is a measure of how much the optimiser may
change the date of an assigned job. A value of 0 means that the job must be assigned on the date given
by the start_time field; a value of 1 means the optimiser is completely free to reschedule the
job; values between 0 and 1 control how close to the originally assigned date the job can be
rescheduled.